# Change Order

Companion to `client-project-agreement.md` §6. Two formats below:

1. **Email version** — paste into an email. Use this for most change orders.
2. **Formal version** — print or PDF. Use for larger changes, or when the client wants a document.

Approval is by email either way. §6.6 requires nothing more than a written reply.

---

## 1. Email version — copy from here

```
Subject: Change Order #{{CO_NUMBER}} — {{PROJECT_NAME}}

Hi {{CLIENT_CONTACT_NAME}},

Following your email on {{REQUEST_DATE}}, here's the change order for that work.

WHAT YOU ASKED FOR
{{REQUEST_SUMMARY}}

WHAT I'LL DO
{{WORK_DESCRIPTION}}

PRICE
{{CO_TOTAL}} — {{PRICE_BASIS}}

EFFECT ON DELIVERY
{{TIMELINE_IMPACT}}

BILLING
{{BILLING_TIMING}}

This is a change order under Section 6 of our agreement dated {{AGREEMENT_DATE}}.
No work starts and nothing is billed until you approve it.

Reply "approved" to this email and I'll get going.

Thanks,
Jaime Aleman
915website LLC
(915) 247-2672 · me@915website.com
```

---

## 2. Formal version

**Change Order #{{CO_NUMBER}}**
**Date:** {{CO_DATE}}

| | |
|---|---|
| Client | {{CLIENT_BUSINESS_NAME}} |
| Project | {{PROJECT_NAME}} |
| Agreement dated | {{AGREEMENT_DATE}} |
| Request received | {{REQUEST_DATE}} |

### Requested

{{REQUEST_SUMMARY}}

### Work to be performed

{{WORK_DESCRIPTION}}

### Price

| | |
|---|---|
| Basis | {{PRICE_BASIS}} |
| **Total** | **{{CO_TOTAL}}** |

Rates under §6.5 of the agreement: additional page matching the site's existing style — $100.00 per page. Genuinely custom work — $50.00 per hour, in 15-minute increments after the first hour.

Where the price is hourly, the total above is an estimate. If the work will exceed the estimate, Designer will stop and send a revised change order before continuing past it.

### Effect on delivery

{{TIMELINE_IMPACT}}

Revised delivery date: {{NEW_DELIVERY_DATE}}

### Billing

{{BILLING_TIMING}}

### Approval

Under §6.6 of the agreement, no work described here begins, and nothing is billed for it, until Client approves in writing. A reply by email is sufficient.

Client approves by replying to this change order at **me@915website.com**, or by signing below.

&nbsp;

**Client**

Signature: _________________________________________ &nbsp;&nbsp; Date: _______________

Printed Name: _________________________________________

&nbsp;

**Designer**

Printed Name: Jaime Aleman &nbsp;&nbsp; Business: 915website LLC

Signature: _________________________________________ &nbsp;&nbsp; Date: _______________

---

## Filling this out

| Field | What goes in it |
|---|---|
| `{{CO_NUMBER}}` | Sequential per project — 001, 002, 003 |
| `{{REQUEST_DATE}}` | Date of the client's email. Always cite their email — it's the record §6.1 exists to create |
| `{{REQUEST_SUMMARY}}` | Their words, quoted or closely paraphrased. Shows you understood the ask |
| `{{WORK_DESCRIPTION}}` | What you'll actually do. Be specific enough that "done" is unambiguous |
| `{{PRICE_BASIS}}` | e.g. `2 additional pages at $100.00 each` or `estimated 3.5 hours at $50.00/hour` |
| `{{CO_TOTAL}}` | The number. If hourly, say "estimated" |
| `{{TIMELINE_IMPACT}}` | e.g. `Adds 3 business days` or `No change to the delivery date` |
| `{{BILLING_TIMING}}` | Before launch: `Added to the final balance due before go-live.` After launch: `Invoiced on completion, due on receipt.` |

**Before sending, check:** is this actually over the 30-minute floor in §6.3? If it's under, do it and don't send a change order. If it's a pile of small items in one email, estimate the pile as a whole — that's the §6.3 rule.